Critical Construction Readiness Factors for Bridge Projects
Abstract
Â
Doi: 10.28991/CEJ-SP2024-010-015
Full Text: PDF
Keywords
References
Montaser, N. M., Mahdi, I. M., Mahdi, H. A., & Rashid, I. A. (2018). Factors Affecting Construction Labor Productivity for Construction of Pre-Stressed Concrete Bridges. International Journal of Construction Engineering and Management, 7(6), 193–206. doi:10.5923/j.ijcem.20180706.01.
State Information Service. (2023). Achievements of the ministry of transportation during 9 years (2014 - 2023). State Information Service, Your gateway to Egypt, Cairo, Egypt.
Choudhry, R. M., Aslam, M. A., Hinze, J. W., & Arain, F. M. (2014). Cost and Schedule Risk Analysis of Bridge Construction in Pakistan: Establishing Risk Guidelines. Journal of Construction Engineering and Management, 140(7), 4014020. doi:10.1061/(asce)co.1943-7862.0000857.
Shrestha, P. P., & Neupane, K. P. (2020). Identification of Geotechnical-Related Problems Impacting Cost, Schedule, and Claims on Bridge Construction Projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 12(2), 4520005. doi:10.1061/(asce)la.1943-4170.0000375.
Zidane, Y. J. T., & Andersen, B. (2018). The top 10 universal delay factors in construction projects. International Journal of Managing Projects in Business, 11(3), 650–672. doi:10.1108/IJMPB-05-2017-0052.
Rosenfeld, Y. (2014). Root-Cause Analysis of Construction-Cost Overruns. Journal of Construction Engineering and Management, 140(1), 4013039. doi:10.1061/(asce)co.1943-7862.0000789.
Asadi, R., Wilkinson, S., & Rotimi, J. O. B. (2023). The common causes of rework in construction contracts: a diagnostic approach. Journal of Engineering, Design and Technology, 21(4), 1107–1133. doi:10.1108/JEDT-04-2021-0215.
Jarkas, A. M., & Bitar, C. G. (2012). Factors Affecting Construction Labor Productivity in Kuwait. Journal of Construction Engineering and Management, 138(7), 811–820. doi:10.1061/(asce)co.1943-7862.0000501.
Ibrahim, M. W., Labib, Y., Veeramani, D., Hanna, A. S., & Russell, J. (2021). Comprehensive Model for Construction Readiness Assessment. Journal of Management in Engineering, 37(1), 4020088. doi:10.1061/(asce)me.1943-5479.0000832.
CSI. (2011). The CSI (Construction Specifications Institute) construction contract administration practice guide. John Wiley & Sons, Hoboken, United States.
Griego, R., & Leite, F. (2016). Investigating Impacts, Drivers, and Leading Indicators of Premature Starts to Construction. Construction Research Congress 2016, 179–188. doi:10.1061/9780784479827.019.
Griego, R., & Leite, F. (2017). Premature Construction Start Interruptions: How Awareness Could Prevent Disputes and Litigations. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 9(2), 4516016. doi:10.1061/(asce)la.1943-4170.0000210.
Ibrahim, M. W. W. (2018). Improving project performance by mitigating out-of-sequence work and assessing construction readiness. PhD Thesis, The University of Wisconsin-Madison, Madison, United States.
Latif, A. A., (2022). About Egypt’s mega projects: Infrastructure & Hayah Kareema. The Egyptian Center for Economic Studies (ECES), Cairo, Egypt. Available online: https://eces.org.eg/en/about-egypts-mega-projects-infrastructure-hayah-kareema/ (accessed on February 2024).
Flyvbjerg, B., Holm, M. K. S., & Buhl, S. L. (2003). How common and how large are cost overruns in transport infrastructure projects? Transport Reviews, 23(1), 71–88. doi:10.1080/01441640309904.
El-Maaty, A.A., Akal, A.Y., El-Hamrawy, S.A. (2018). The Iron Triangle of Projects Management: Quality, Schedule and Cost of Road Infrastructure Projects in Egypt. Towards Sustainable Cities in Asia and the Middle East, GeoMEast 2017, Sustainable Civil Infrastructures, Springer, Cham, Switzerland. doi:10.1007/978-3-319-61645-2_1.
Ammar, T., Abdel-Monem, M., & El-Dash, K. (2022). Risk factors causing cost overruns in road networks. Ain Shams Engineering Journal, 13(5), 101720. doi:10.1016/j.asej.2022.101720.
Hiyassat, M. A., Alkasagi, F., El-Mashaleh, M., & Sweis, G. J. (2022). Risk allocation in public construction projects: the case of Jordan. International Journal of Construction Management, 22(8), 1478–1488. doi:10.1080/15623599.2020.1728605.
Ashmawi, K., Hadidi, L. A., Assaf, S., Tuffaha, F. M., & Al-Ofi, K. (2018). Risk assessment and allocation in the contract for public works used in Saudi Arabia construction industry. Cogent Engineering, 5(1), 1490148. doi:10.1080/23311916.2018.1490148.
Construction Industry Institute. (2018). Construction readiness assessment for productivity improvement. Construction Industry Institute, Austin, United States. Available online: https://www.construction-institute.org/construction-readiness-assessment-for-productivity-improvement (accessed on 7 April 2024).
Radzi, A. R., Rahman, R. A., Doh, S. I., & Esa, M. (2022). Construction Readiness for Highway Projects: Key Decision Criteria. Journal of Construction Engineering and Management, 148(2), 4021196. doi:10.1061/(asce)co.1943-7862.0002237.
Abdul-Rahman, N. A., Rahman, R. A., & Alias, A. R. (2024). Modeling the construction readiness parameters for abandoned housing projects in Malaysia: PLS-SEM approach. Open House International, 49(5), 904–926. doi:10.1108/ohi-10-2023-0227.
Radzi, A. R., Azmi, N. F., Kamaruzzaman, S. N., Algahtany, M., & Rahman, R. A. (2024). Challenges in construction readiness for BIM-based building projects. Journal of Asian Architecture and Building Engineering, 1–16. doi:10.1080/13467581.2024.2343803.
Construction Industry Institute, (2016). Identifying drivers, leading indicators, and impacts of premature starts to construction: A quantitative and qualitative approach. Construction Industry Institute, Austin, United States. Available online: https://www.construction-institute.org/identifying-drivers-leading-indicators-and-impacts-of-premature-starts-to-construction-a-quantita (accessed on May 2024).
Leite, F. L., & Griego, R. (2019). Premature Start Impact Analysis Tool: Preventing Unintended Construction Interruptions and Associated Impacts. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 11(2), 4519005. doi:10.1061/(asce)la.1943-4170.0000291.
de la Garza, J. M., & Pishdad-Bozorgi, P. (2018). Workflow Process Model for Flash Track Projects. Journal of Construction Engineering and Management, 144(6), 6018001. doi:10.1061/(asce)co.1943-7862.0001501.
Construction Industry Institute, (2015). Successful delivery of flash-track projects. Construction Industry Institute, Austin, United States. Available online: https://www.construction-institute.org/successful-delivery-of-flash-track-projects (accessed on May 2024).
Austin, R. B., Pishdad-Bozorgi, P., & de la Garza, J. M. (2016). Identifying and Prioritizing Best Practices to Achieve Flash Track Projects. Journal of Construction Engineering and Management, 142(2), 4015077. doi:10.1061/(asce)co.1943-7862.0001061.
Pishdad-Bozorgi, P., de la Garza, J. M., & Austin, R. B. (2016). Readiness Assessment for Flash Tracking. Journal of Construction Engineering and Management, 142(12), 6016005. doi:10.1061/(asce)co.1943-7862.0001190.
Dumont, P. R., Gibson, G. E., & Fish, J. R. (1997). Scope Management Using Project Definition Rating Index. Journal of Management in Engineering, 13(5), 54–60. doi:10.1061/(asce)0742-597x(1997)13:5(54).
Bingham, E., & Gibson, G. E. (2017). Infrastructure Project Scope Definition Using Project Definition Rating Index. Journal of Management in Engineering, 33(2), 4016037. doi:10.1061/(asce)me.1943-5479.0000483.
Burke, R., Parrish, K., & Gibson, G. E. (2016). Defining Small Projects in Developing the PDRI for Small Infrastructure Projects. Construction Research Congress 2016, 159–167. doi:10.1061/9780784479827.017.
Cho, C.-S., & Gibson, G. E. (2001). Building Project Scope Definition Using Project Definition Rating Index. Journal of Architectural Engineering, 7(4), 115–125. doi:10.1061/(asce)1076-0431(2001)7:4(115).
Collins, W., Parrish, K., & Gibson, G. E. (2017). Development of a Project Scope Definition and Assessment Tool for Small Industrial Construction Projects. Journal of Management in Engineering, 33(4), 4017015. doi:10.1061/(asce)me.1943-5479.0000514.
Dicks, E., Molenaar, K. R., & Gibson, G. E. (2017). Scope Definition of Air Force Design and Construction Projects. Journal of Management in Engineering, 33(5), 4017028. doi:10.1061/(asce)me.1943-5479.0000543.
Weerasinghe, G., Soundararajan, K., & Ruwanpura, J. (2007). LEED-PDRI framework for pre-project planning of sustainable building projects. Journal of Green Building, 2(3), 123–143. doi:10.3992/jgb.2.3.123.
Radzi, A. R., Rahman, R. A., Doh, S. I., & Esa, M. (2020). Construction readiness parameters for highway projects. IOP Conference Series: Materials Science and Engineering, 712(1), 12029. doi:10.1088/1757-899X/712/1/012029.
Radzi, A. R., Rahman, R. A., Doh, S. I., & Esa, M. (2021). A Comparative Study on the Readiness Parameters of Highway Construction Projects. IOP Conference Series: Earth and Environmental Science, 641(1), 12008. doi:10.1088/1755-1315/641/1/012008.
Abdul-Rahman, N. A., Rahman, R. A., & Alias, A. R. (2023). Decision Criteria for Assessing Construction Readiness of Abandoned Projects. AIP Conference Proceedings, 2688(1). doi:10.1063/5.0111291.
Zhang, N., Hwang, B. G., Deng, X., & Tay, F. (2024). Exploring critical success factors for collaborative contracting implementation in the Singapore construction industry. Engineering, Construction and Architectural Management, 31(2), 919–938. doi:10.1108/ECAM-05-2022-0398.
Homthong, S., Moungnoi, W., & Charoenngam, C. (2024). Whole Life Critical Factors Influencing Construction Project Performance for Different Objectives: Evidence from Thailand. Buildings, 14(4), 999. doi:10.3390/buildings14040999.
Gupta, S., Jha, K. N., & Vyas, G. (2024). Construction and demolition waste causative factors in building projects: survey of the Indian construction industry experiences. International Journal of Construction Management, 24(4), 432–442. doi:10.1080/15623599.2022.2111962.
Zhao, X., Hwang, B.-G., Pheng Low, S., & Wu, P. (2015). Reducing Hindrances to Enterprise Risk Management Implementation in Construction Firms. Journal of Construction Engineering and Management, 141(3), 4014083. doi:10.1061/(asce)co.1943-7862.0000945.
Robson, C. and McCartan, K. (2016). Real world research: A resource for users of social research methods in applied settings (4th Ed.). John Wiley & Sons, Chichester, United Kingdom.
Obilor, E. I. (2023). Convenience and purposive sampling techniques: Are they the same. International Journal of Innovative Social & Science Education Research, 11(1), 1-7.
Johnson, T. P. (2014). Snowball Sampling: Introduction. Wiley StatsRef: Statistics Reference Online. John Wiley & Sons, Hoboken, United States. doi:10.1002/9781118445112.stat05720.
Parker, C., Scott, S., & Geddes, A. (2019). Snowball sampling. SAGE research methods foundations. University Of Gloucestershire, Cheltenham, United Kingdom.
Etikan, I. (2016). Comparision of Snowball Sampling and Sequential Sampling Technique. Biometrics & Biostatistics International Journal, 3(1), 55. doi:10.15406/bbij.2016.03.00055.
Kukah, A. S. K., Owusu-Manu, D. G., Badu, E., & Edwards, D. J. (2024). Exploring influencing factors for private sector participation in PPP power projects: case of Ghana. Journal of Facilities Management, 22(2), 310–324. doi:10.1108/JFM-11-2021-0140.
Ahmed, S., & El-Sayegh, S. (2024). Relevant criteria for selecting project delivery methods in sustainable construction. International Journal of Construction Management, 24(5), 512–520. doi:10.1080/15623599.2023.2179609.
Wang, D., Jia, J., Jiang, S., Liu, T., & Ma, G. (2023). How Team Voice Contributes to Construction Project Performance: The Mediating Role of Project Learning and Project Reflexivity. Buildings, 13(7), 1599. doi:10.3390/buildings13071599.
El-Kholy, A. M., & Akal, A. Y. (2021). Determining the stationary financial cause of contracting firms failure. International Journal of Construction Management, 21(8), 818–833. doi:10.1080/15623599.2019.1584836.
Yashiro, Y., Ueda, R., Hatori, F., Yabuki, N. (2021). An Interview-Based Method for Extracting Knowledge of Skilled Workers at Construction Sites Using Photographs and Deep Learning. Proceedings of the 18th International Conference on Computing in Civil and Building Engineering. ICCCBE 2020, Lecture Notes in Civil Engineering, 98, Springer, Cham, Switzerland. doi:10.1007/978-3-030-51295-8_3.
Forza, C. (2002). Survey research in operations management: A process-based perspective. International Journal of Operations and Production Management, 22(2), 152–194. doi:10.1108/01443570210414310.
Miller, D. C. (1967). Handbook of research design and social measurement. Sage Publications, Thousand Oaks, United States.
Darko, A., Chan, A. P. C., Gyamfi, S., Olanipekun, A. O., He, B. J., & Yu, Y. (2017). Driving forces for green building technologies adoption in the construction industry: Ghanaian perspective. Building and Environment, 125, 206–215. doi:10.1016/j.buildenv.2017.08.053.
Ahmadabadi, A. A., & Heravi, G. (2019). The effect of critical success factors on project success in Public-Private Partnership projects: A case study of highway projects in Iran. Transport Policy, 73, 152–161. doi:10.1016/j.tranpol.2018.07.004.
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of Delay in Building Construction Projects in Egypt. Journal of Construction Engineering and Management, 134(11), 831–841. doi:10.1061/(asce)0733-9364(2008)134:11(831).
Adabre, M. A., & Chan, A. P. C. (2019). Critical success factors (CSFs) for sustainable affordable housing. Building and Environment, 156, 203–214. doi:10.1016/j.buildenv.2019.04.030.
Islam, M. S., & Suhariadi, B. T. (2018). Construction delays in privately funded large building projects in Bangladesh. Asian Journal of Civil Engineering, 19(4), 415–429. doi:10.1007/s42107-018-0034-3.
Kshaf, D. A., Mohamed, M. A., & El-Dash, K. M. (2022). The major problems between main contractors and subcontractors in construction projects in Egypt. Ain Shams Engineering Journal, 13(6), 101813. doi:10.1016/j.asej.2022.101813.
Derakhshanalavijeh, R., & Teixeira, J. M. C. (2017). Cost overrun in construction projects in developing countries, Gas-Oil industry of Iran as a case study. Journal of Civil Engineering and Management, 23(1), 125–136. doi:10.3846/13923730.2014.992467.
Le-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering, 12(6), 367–377. doi:10.1007/s12205-008-0367-7.
Yamany, M. S., Abdelhameed, A., Elbeltagi, E., & Mohamed, H. A. E. (2024). Critical success factors of infrastructure construction projects. Innovative Infrastructure Solutions, 9(4), 95. doi:10.1007/s41062-024-01394-9.
Field, A. (2013). Discovering Statistics Using IBM SPSS Statistics: And Sex and Drugs and Rock “N†Roll (4th Edition). SAGE Publications, SAGE Publications, New Delhi, India.
Shalabi, L. Al, Shaaban, Z., & Kasasbeh, B. (2006). Data Mining: A Preprocessing Engine. Journal of Computer Science, 2(9), 735–739. doi:10.3844/jcssp.2006.735.739.
Ali, P. J. M., Faraj, R. H., Koya, E., Ali, P. J. M., & Faraj, R. H. (2014). Data normalization and standardization: a technical report. Machine Learning Technical Reports, 1(1), 1-6.
Kwak, S. K., & Kim, J. H. (2017). Statistical data preparation: Management of missing values and outliers. Korean Journal of Anesthesiology, 70(4), 407–411. doi:10.4097/kjae.2017.70.4.407.
Sijtsma, K., & Van Der Ark, L. A. (2015). Conceptions of reliability revisited and practical recommendations. Nursing Research, 64(2), 128–136. doi:10.1097/NNR.0000000000000077.
Tavakol, M., & Dennick, R. (2011). Making sense of Cronbach’s alpha. International Journal of Medical Education, 2, 53–55. doi:10.5116/ijme.4dfb.8dfd.
McCrae, R. R., Kurtz, J. E., Yamagata, S., & Terracciano, A. (2011). Internal consistency, retest reliability, and their implications for personality scale validity. Personality and Social Psychology Review, 15(1), 28–50. doi:10.1177/1088868310366253.
Cronbach, L. J. (1951). Coefficient alpha and the internal structure of tests. Psychometrika, 16(3), 297–334. doi:10.1007/BF02310555.
Bonett, D. G., & Wright, T. A. (2015). Cronbach’s alpha reliability: Interval estimation, hypothesis testing, and sample size planning. Journal of Organizational Behavior, 36(1), 3–15. doi:10.1002/job.1960.
Bland, J. M., & Altman, D. G. (1997). Statistics notes: Cronbach’s alpha. BMJ, 314(7080), 572. doi:10.1136/bmj.314.7080.572.
Nunnally, J., & Bernstein, I. (1994). Psychometric Theory (3rd d.). MacGraw-Hill, New York, United States.
Sthle, L., & Wold, S. (1989). Analysis of variance (ANOVA). Chemometrics and Intelligent Laboratory Systems, 6(4), 259–272. doi:10.1016/0169-7439(89)80095-4.
Blanca, M. J., Alarcón, R., Arnau, J., Bono, R., & Bendayan, R. (2018). Effect of variance ratio on ANOVA robustness: Might 1.5 be the limit? Behavior Research Methods, 50(3), 937–962. doi:10.3758/s13428-017-0918-2.
Ostertagová, E., Ostertag, O., & KováÄ, J. (2014). Methodology and application of the Kruskal-Wallis test. Applied Mechanics and Materials, 611, 115–120. doi:10.4028/www.scientific.net/AMM.611.115.
McKight, P. E., & Najab, J. (2010). Kruskal-Wallis Test. The Corsini Encyclopedia of Psychology, John Wiley & Sons, Hoboken, United States. doi:10.1002/9780470479216.corpsy0491.
Kruskal, W. H., & Wallis, W. A. (1952). Use of Ranks in One-Criterion Variance Analysis. Journal of the American Statistical Association, 47(260), 583–621. doi:10.1080/01621459.1952.10483441.
Kruskal, W. H. (1952). A Nonparametric test for the Several Sample Problem. The Annals of Mathematical Statistics, 23(4), 525–540. doi:10.1214/aoms/1177729332.
Triola, M. F. (2009). Elementary statistics (11th Ed.). Addison Wesley, Boston, United States.
Dunn, O. J. (1964). Multiple Comparisons using Rank Sums. Technometrics, 6(3), 241–252. doi:10.1080/00401706.1964.10490181.
Hauke, J., & Kossowski, T. (2011). Comparison of values of pearson’s and spearman’s correlation coefficients on the same sets of data. Quaestiones Geographicae, 30(2), 87–93. doi:10.2478/v10117-011-0021-1.
Mukaka, M. M. (2012). A guide to appropriate use of correlation coefficient in medical research. Malawi Medical Journal, 24(3), 69-71.
Ursachi, G., Horodnic, I. A., & Zait, A. (2015). How Reliable are Measurement Scales? External Factors with Indirect Influence on Reliability Estimators. Procedia Economics and Finance, 20, 679–686. doi:10.1016/s2212-5671(15)00123-9.
Yadav, B.P., Siddiqui, N.A., Jain, S., Nayar, D.V. (2023). Utility Damage Prevention Measures During Excavation: A Review. Advances in Construction Safety. Springer, Singapore. doi:10.1007/978-981-19-4001-9_4.
Al-Bayati, A. J., Panzer, L., & Karakhan, A. (2019). Reducing Damages to Underground Infrastructure: Performance Evaluation of One-Call Notification Program. Practice Periodical on Structural Design and Construction, 24(4), 4019018. doi:10.1061/(asce)sc.1943-5576.0000441.
Lew, J. J., & Anspach, J. (2000). Elimination of utility line cuts on a highway project using subsurface utility engineering. Designing for Safety and Health, 26-27 June, 2000, London, United Kingdom.
Al-Bayati, A. J., & Panzer, L. (2019). Reducing Damage to Underground Utilities: Lessons Learned from Damage Data and Excavators in North Carolina. Journal of Construction Engineering and Management, 145(12), 4019078. doi:10.1061/(asce)co.1943-7862.0001724.
Al-Bayati, A. J., Panzer, L., & Kaddoura, K. (2020). Minimizing Underground Infrastructure Damages: Utility Locators’ Perspectives. Pipelines 2020, 387–391. doi:10.1061/9780784483213.043.
Reid, J. (1999). Are contractors, engineers, and architects ready for a crisis?. Cost Engineering, 41(3), 14..
Tanoli, W. A., Sharafat, A., Park, J., & Seo, J. W. (2019). Damage Prevention for underground utilities using machine guidance. Automation in Construction, 107, 102893. doi:10.1016/j.autcon.2019.102893.
Li, Y., & Liu, C. (2019). Applications of multirotor drone technologies in construction management. International Journal of Construction Management, 19(5), 401–412. doi:10.1080/15623599.2018.1452101.
Ezeomedo, I. (2019). Role of land surveyors and geospatial engineers in the built environment. COOU African Journal of Environmental Research, 2(1), 102-117.
Kavanagh, B. F., & Slattery, D. K. (2010). Surveying: with construction applications. Pearson, Upper Saddle River, United States.
Arain, F. M., Pheng, L. S., & Assaf, S. A. (2006). Contractors’ Views of the Potential Causes of Inconsistencies between Design and Construction in Saudi Arabia. Journal of Performance of Constructed Facilities, 20(1), 74–83. doi:10.1061/(asce)0887-3828(2006)20:1(74).
Yates, J. K., & Epstein, A. (2006). Avoiding and minimizing construction delay claim disputes in relational contracting. Journal of Professional Issues in Engineering Education and Practice, 132(2), 168–179. doi:10.1061/(ASCE)1052-3928(2006)132:2(168).
Goldsworthy, J. S., Jaksa, M. B., Fenton, G. A., Griffiths, D. V., Kaggwa, W. S., & Poulos, H. G. (2007). Measuring the Risk of Geotechnical Site Investigations. Proceedings of Geo-Denver 2007: New Peaks in Geotechnics, 1–12. doi:10.1061/40914(233)2.
Olanrewaju, B. A., Panesar, D. K., & Saxe, S. (2022). A comparison of concrete quantities for highway bridge projects: preconstruction estimates vs onsite records. Sustainable and Resilient Infrastructure, 7(5), 589–605. doi:10.1080/23789689.2021.1980299.
Vilventhan, A., & Kalidindi, S. N. (2012). Approval Risks in Transportation Infrastructure Projects in India. Construction Research Congress 2012, 2250–2259. doi:10.1061/9780784412329.226.
Ehwany, N. E. (2011). The Construction and Related Engineering Services in Egypt: Challenges and Policies. Toward More Efficient Services in Egypt Reforming Tourism, Construction, Information Technology, Wholesale and Retail, Roads, and Banking Services, 103–154, Oxford University Press, Oxford, United Kingdom. doi:10.5743/cairo/9789774164941.003.0004.
Ding, C. (2007). Policy and praxis of land acquisition in China. Land Use Policy, 24(1), 1–13. doi:10.1016/j.landusepol.2005.09.002.
Food and Agriculture Organization of the United Nations (FAO). (2008). Compulsory acquisition of land and compensation. Food and Agriculture Organization of the United Nations (FAO), Rome, Italy.
Elawi, G. S. A., Algahtany, M., & Kashiwagi, D. (2016). Owners’ Perspective of Factors Contributing to Project Delay: Case Studies of Road and Bridge Projects in Saudi Arabia. Procedia Engineering, 145, 1402–1409. doi:10.1016/j.proeng.2016.04.176.
Zaneldin, E. (2016). Preventing Coordination Problems during the Design Stage of Projects. International Journal of Engineering Research & Science, 2(9), 40–53.
Shen, F. Y., & Chang, A. S. (2008). Exploring coordination goals of construction projects. EASEC-11 - Eleventh East Asia-Pacific Conference on Structural Engineering and Construction, 27(2), 90–96. doi:10.1061/(asce)me.1943-5479.0000046.
Adrian, A. M., Utamima, A., & Wang, K. J. (2015). A comparative study of GA, PSO and ACO for solving construction site layout optimization. KSCE Journal of Civil Engineering, 19(3), 520–527. doi:10.1007/s12205-013-1467-6.
Elbeltagi, E., Hegazy, T., & Eldosouky, A. (2004). Dynamic Layout of Construction Temporary Facilities Considering Safety. Journal of Construction Engineering and Management, 130(4), 534–541. doi:10.1061/(asce)0733-9364(2004)130:4(534).
Tommelein, I. D., Levitt, R. E., & Hayesâ€Roth, B. (1992). Siteâ€Layout Modeling: How Can Artificial Intelligence Help? Journal of Construction Engineering and Management, 118(3), 594–611. doi:10.1061/(asce)0733-9364(1992)118:3(594).
Tao, G., Feng, H., Feng, J., & Wang, T. (2022). Dynamic Multi-objective Construction Site Layout Planning Based on BIM. KSCE Journal of Civil Engineering, 26(4), 1522–1534. doi:10.1007/s12205-022-0708-y.
Hawarneh, A. Al, Bendak, S., & Ghanim, F. (2021). Construction site layout planning problem: Past, present and future. Expert Systems with Applications, 168, 114247. doi:10.1016/j.eswa.2020.114247.
Sanad, H. M., Ammar, M. A., & Ibrahim, M. E. (2008). Optimal Construction Site Layout Considering Safety and Environmental Aspects. Journal of Construction Engineering and Management, 134(7), 536–544. doi:10.1061/(asce)0733-9364(2008)134:7(536).
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. doi:10.1016/j.ijproman.2006.11.007.
Sumner, M., & Slattery, D. (2010). The impact of leadership effectiveness and team processes on team performance in construction. International Journal of Construction Education and Research, 6(3), 179–201. doi:10.1080/15578771.2010.507720.
Wilkinson, A., Johnstone, S., & Townsend, K. (2012). Changing patterns of human resource management in construction. Construction Management and Economics, 30(7), 507–512. doi:10.1080/01446193.2012.711562.
Marzouk, M., & Elsayed, A. (2024). Framework for assessing bridges construction impact on work zone traffic using BRIM. Scientific Reports, 14(1), 83. doi:10.1038/s41598-023-50404-w.
Elbehairy, H., Hegazy, T., & Souki, K. (2006). Bridge management system with practical work zone planning. Joint International Conference on Computing and Decision Making in Civil and Building Engineering, 14-16 June, Montreal, Canada.
Fisk, E. R. & Reynolds, W. D. (2010). Construction project administration (9th Ed.). Prentice Hall, Upper Saddle River, United States.
Cakmak, E., & Cakmak, P. I. (2014). An Analysis of Causes of Disputes in the Construction Industry Using Analytical Network Process. Procedia - Social and Behavioral Sciences, 109, 183–187. doi:10.1016/j.sbspro.2013.12.441.
Rashid, R. A., Mustapa, M., & Wahid, S. N. A. (2006). Bills of Quantities-Are they still useful and relevant today. International conference on construction industry, 21-25 June, 2006, Padang, Indonesia.
Francis, M., Ramachandra, T., & Perera, S. (2022). Disputes in Construction Projects: A Perspective of Project Characteristics. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 14(2), 4522007. doi:10.1061/(asce)la.1943-4170.0000535.
Farzad Moosavi, S., & Moselhi, O. (2014). Review of Detailed Schedules in Building Construction. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 6(3), 5014001. doi:10.1061/(asce)la.1943-4170.0000142.
Bagaya, O., & Song, J. (2016). Empirical Study of Factors Influencing Schedule Delays of Public Construction Projects in Burkina Faso. Journal of Management in Engineering, 32(5), 5016014. doi:10.1061/(asce)me.1943-5479.0000443.
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), 4015032. doi:10.1061/(asce)me.1943-5479.0000391.
Nguyen, L. D., Ogunlana, S. O., & Lan, D. T. X. (2004). A study on project success factors in large construction projects in Vietnam. Engineering, Construction and Architectural Management, 11(6), 404–413. doi:10.1108/09699980410570166.
Sakurai, Y., Mayhew, P., and White, M. (2008). Theft and vandalism at residential building sites in Australia. Australian Institute of Criminology, Canberra, Australia.
Haas, O., Huschbeck, T., MarkoviÄ, P. (2022). Effects of Theft on the Critical Path of Construction Projects. Developments in Information & Knowledge Management for Business Applications. Studies in Systems, Decision and Control, 420, Springer, Cham, Switzerland. doi:10.1007/978-3-030-95813-8_3.
Ablordeppey, E. E., Moo, F., Akortsu, W., & Mustapha, A. (2020). Minimizing Theft on Construction Sites in Ghana: The Perspective of Contractors in the Upper West Region of Ghana. Civil and Environmental Research, 12(5), 24–57. doi:10.7176/cer/12-5-03.
Chung, H. W. (2002). Understanding Quality Assurance in Construction. Routledge, London, United Kingdom. doi:10.4324/9780203015834.
Abeku, D. M., Ogunbode, E. B., Salihu, C., Maxwell, S. S., & Kure, M. A. (2016). Projects Management and the effect of Rework on Construction Works : A Case of selected Projects in Abuja Metropolis , Nigeria. International Journal of Finance and Management in Practice, 4(1), 38–46.
DOI: 10.28991/CEJ-SP2024-010-015