Development of a Prediction System for Design Defects of Buildings

Ahmed Nouh, El-Sayed El-Kasaby, Khaled Aboulata

Abstract


The research aimed to establish a quantitative model to predict the occurrence of five types of design defects: unsafe design, incompatible design, inefficient design, design ambiguity, and design delays. It also examined the contractor's liability for design to determine who is ultimately responsible for design defects disputes between the employer and contractor. The study employed a descriptive methodology to identify fifteen potential influencing factors on design defects. Data were collected from 42 construction projects and tested using Design of Experiments (DOE). Out of these fifteen factors, only five—design schedule, design firm experience, stakeholders’ involvement, project delivery system, and information accuracy—had a significant impact on design defects. These factors were used in the development of a new model to predict the occurrence of design defects. The model was validated using data that was held separate from the model development process for validation purposes. The calculated Mean Absolute Percentage of Error (MAPE) for the new model is 19%, which is considered a "good" prediction accuracy. The research achieved three significant milestones: 1) It identified the ultimate responsibility for the consequences of design defects in construction projects across different jurisdictions. This information can be used to resolve potential disputes between employers, designers, and contractors’ organizations. 2) It provided guidelines on how to minimize design defects in construction projects, thereby mitigating the consequences of such defects. 3) It developed a new model to predict the occurrence of design defects in construction projects. This model aids decision-makers in responsible organizations during the process of predicting the appropriate reserve to be added to the project schedule and budget. Consequently, it helps mitigate the risk of design defect-related delays and cost overruns.

 

Doi: 10.28991/CEJ-SP2023-09-017

Full Text: PDF


Keywords


Design Defects; Design Responsibility; Design of Experiment (DOE); Contractor Design Liability; Cost of Poor Quality.

References


Abolnour, M. M. (1994). The relationship of fee structure in engineering offices and design deficiency. Master Thesis, King Fahd University of Petroleum and Minerals, Dhahran, Kingdom of Saudi Arabia.

Andi, & Minato, T. (2003). Design documents quality in the Japanese construction industry: Factors influencing and impacts on construction process. International Journal of Project Management, 21(7), 537–546. doi:10.1016/S0263-7863(02)00083-2.

American Society of Civil Engineers (ASCE). (2012). Quality in the Constructed Project. American Society of Civil Engineers (ASCE), Reston, United States. doi:10.1061/9780784411896.

Bubshait, A. A., & Al-Abdulrazzak, A. (1996). Design quality management activities. Journal of Professional Issues in Engineering Education and Practice, 122(3), 104–106. doi:10.1061/(ASCE)1052-3928(1996)122:3(104).

Darwish, M. I. (2005). Factors affecting design and documentation quality in construction industry. Master Thesis, King Fahd University of Petroleum and Minerals, Dhahran, Kingdom of Saudi Arabia.

Lam, P. T. I., Wong, F. W. H., & Chan, A. P. C. (2006). Contributions of designers to improving buildability and constructability. Design Studies, 27(4), 457–479. doi:10.1016/j.destud.2005.10.003.

Tilley, P. A., & Barton, R. (1997). Design and documentation deficiency-causes and effects. Proceedings of the First International Conference of Construction Process Reengineering, 14-15 July, 1997, Gold Coast, Australia.

Lu, Y., Sood, T., Chang, R., & Liao, L. (2020). Factors impacting integrated design process of net zero energy buildings: an integrated framework. International Journal of Construction Management, 22(9), 1700–1712. doi:10.1080/15623599.2020.1742625.

Kamal, A., Abas, M., Khan, D., & Azfar, R. W. (2022). Risk factors influencing the building projects in Pakistan: from perspective of contractors, clients and consultants. International Journal of Construction Management, 22(6), 1141–1157. doi:10.1080/15623599.2019.1683693.

Gashaw, T., & Jilcha, K. (2023). Design risk modeling and analysis for railway construction projects. International Journal of Construction Management, 23(14), 2488–2498. doi:10.1080/15623599.2022.2070344.

Hamzah, N., Ramly, A., Salleh, H., Tawil, N. M., Khoiry, M. A., & Che Ani, A. I. (2011). The importance of design process in housing quality. Procedia Engineering, 20, 483–489. doi:10.1016/j.proeng.2011.11.191.

Chong, W.-K., & Low, S.-P. (2006). Latent Building Defects: Causes and Design Strategies to Prevent Them. Journal of Performance of Constructed Facilities, 20(3), 213–221. doi:10.1061/(asce)0887-3828(2006)20:3(213).

Koo, H. J., & O’Connor, J. T. (2022). Building information modeling as a tool for prevention of design defects. Construction Innovation, 22(4), 870–890. doi:10.1108/CI-02-2021-0033.

Marzouk, M., ElSharkawy, M., & Mahmoud, A. (2022). Analysing user daylight preferences in heritage buildings using virtual reality. Building Simulation, 15(9), 1561–1576. doi:10.1007/s12273-021-0873-9.

Chen, G., Chen, J., Yuan, J., Tang, Y., Xiahou, X., & Li, Q. (2022). Exploring the Impact of Collaboration on BIM Use Effectiveness: A Perspective through Multiple Collaborative Behaviors. Journal of Management in Engineering, 38(6). doi:10.1061/(asce)me.1943-5479.0001098.

Ali, A. S., Keong, K. C., Zakaria, N., Zolkafli, U., & Akashah, F. (2013). The effect of design on maintenance for school buildings in Penang, Malaysia. Structural Survey, 31(3), 194–201. doi:10.1108/SS-10-2012-0030.

Zheng, H., Liu, W., & Xiao, C. (2018). Structural relationship model for design defect and influencing factors in the concurrent design process. International Journal of Production Research, 56(14), 4897–4924. doi:10.1080/00207543.2018.1447704.

Waziri, B. S. (2016). Design and construction defects influencing residential building maintenance in Nigeria. Jordan Journal of Civil Engineering, 10(3), 313–323. doi:10.14525/JJCE.10.3.3605.

Minato, T. (2003). Representing causal mechanism of defective designs: a system approach considering human errors. Construction Management and Economics, 21(3), 297–305. doi:10.1080/0144619032000056135.

Tayeh, B. A., Hamad, R. J. A., Alaloul, W. S., & Almanassra, M. (2019). Factors Affecting Defects Occurrence in Structural Design Stage of Residential Buildings in Gaza Strip. The Open Civil Engineering Journal, 13(1), 129–139. doi:10.2174/1874149501913010129.

Gransberg, D. D., & Molenaar, K. (2004). Analysis of Owner’s Design and Construction Quality Management Approaches in Design/Build Projects. Journal of Management in Engineering, 20(4), 162–169. doi:10.1061/(asce)0742-597x(2004)20:4(162).

Wu, H., Zhong, B., Li, H., Guo, J., & Wang, Y. (2021). On-Site Construction Quality Inspection Using Blockchain and Smart Contracts. Journal of Management in Engineering, 37(6), 04021065. doi:10.1061/(asce)me.1943-5479.0000967.

Josephson, P. E. (1998). Defects and defect costs in construction. Working Paper, Department of Management of

Construction and Facilities, Chalmers University of Technology, Gothenburg, Sweden.

O’Connor, J. T., & Koo, H. J. (2021). Proactive Design Quality Assessment Tool for Building Projects. Journal of Construction Engineering and Management, 147(2), 04020174. doi:10.1061/(asce)co.1943-7862.0001980.

Lee, J.-S. (2018). Value Engineering for Defect Prevention on Building Façade. Journal of Construction Engineering and Management, 144(8), 04018069. doi:10.1061/(asce)co.1943-7862.0001500.

Jiang, Q., Qiang, M., & Lin, C. (2022). Collaborative Evaluation Method of Multiple Team Membership: Case Study of Engineering Design Company. Journal of Management in Engineering, 38(6), 05022014. doi:10.1061/(asce)me.1943-5479.0001096.

Faqih, F., & Zayed, T. (2021). Defect-based building condition assessment. Building and Environment, 191, 107575. doi:10.1016/j.buildenv.2020.107575.

Lupășteanu, V., Lupășteanu, R., & Chingălată, C. (2022). Condition assessment of buildings in Romania: A proposed method and case study. Journal of Building Engineering, 47. doi:10.1016/j.jobe.2021.103814.

Gabaldón, L. B. F. (2017). Rehabilitation and lessons learned from the collapse of Viaduct 1 located on the Caracas-La-Guaira Highway in Venezuela. Structural Engineering International: Journal of the International Association for Bridge and Structural Engineering (IABSE), 27(3), 380–387. doi:10.2749/101686617X14881937385007.

Madaj, A., & Siekierski, W. (2017). Determination of defect factors for a road bridge made of prestressed concrete. Structural Engineering International: Journal of the International Association for Bridge and Structural Engineering (IABSE), 27(3), 388–393. doi:10.2749/101686617X14881932436735.

Abu-Reishah, L., & Hiyassat, M. A. (2023). The severity of design-construction interface risks in Jordanian construction industry. International Journal of Construction Management, 23(9), 1540–1548. doi:10.1080/15623599.2021.1983930.

Xu, X., & Zou, P. X. (2020). Analysis of factors and their hierarchical relationships influencing building energy performance using interpretive structural modelling (ISM) approach. Journal of Cleaner Production, 272, 122650. doi:10.1016/j.jclepro.2020.122650.

Hassanain, M. A., Al-Hammad, A. M., & Fatayer, F. (2014). Assessment of architectural defects attributed to lack of maintenance feedback to the design team. Architectural Science Review, 57(2), 132–138. doi:10.1080/00038628.2013.783459.

Cruz, P. J. S., Topczewski, L., Fernandes, F. M., Trela, C., & Lourenço, P. B. (2010). Application of radar techniques to the verification of design plans and the detection of defects in concrete bridges. Structure and Infrastructure Engineering, 6(4), 395–407. doi:10.1080/15732470701778506.

Vafeas, M., & Hilton, T. (2002). Client Defection in the Design Industry: A Study of the Causes, Process and Context of Switching Agencies. The Design Journal, 5(1), 14–25. doi:10.2752/146069202789378431.

Qureshi, A. R. (1987). Designer’s Responsibility. Safety and Reliability, 7(2), 28–29. doi:10.1080/09617353.1987.11691147.

Beade-Pereda, H. (2017). The Responsibility of the Bridge Designer. Structural Engineering International, 27(3), 337–337. doi:10.1080/10168664.2017.11985640.

Reich, T. (1959). Responsibility of the designer to-day. Journal of the Textile Institute Proceedings, 50(7), P330–P336. doi:10.1080/19447015908664268.

Eekels, J. (1994). The Engineer as Designer and as a Morally Responsible Individual. Journal of Engineering Design, 5(1), 7–23. doi:10.1080/09544829408907868.

Davey, C. L., McDonald, J., Lowe, D., Duff, R., Powell, J. A., & Powell, J. E. (2006). Defects liability management by design. Building Research and Information, 34(2), 145–153. doi:10.1080/09613210500492991.

Egyptian Civil Code (1952). The Egyptian civil code, promulgated by Law No. 131 of 1948 in force since 15 October 1949. Cairo, Egypt.

Al-Sanhouri, A.A. (1998). Al-Waseet in Explanation of the New Civil Code. Part 1, Volume 2, Al-Halabi Legal Publications, Beirut, Lebanon.

Qatar Civil Code (2004). Qatar Civil Code Act No. 22/2004. Qatari Legal Portal (Al-Meezan), Doha, Qatar.

Kuwait Civil Code (1980). Kuwait Civil Code Act No. 67/1980. Kuwait Govermnet, Kuwait City, Kuwait.

FIDIC. (1987). FIDIC Red Book (4th Ed.), Geneva, Switzerland. Available online: https://fidic.org/books/red-book-1987-red-book-guide-1st-ed-1989 (accessed on June 2023).

FIDIC. (1999). FIDIC Red Book. Geneva, Switzerland. Available online: https://fidic.org/books/construction-contract-1st-ed-1999-red-book (accessed on June 2023).

Eggleston, B. (2008). The ICE Conditions of Contract. Wiley, Blackwell Publishing, New Jersey, United States.

Hawker, G. (1999). ICE Conditions of Contract. Thomas Telford Ltd, London, England.

Egyptian Government (1988). Egyptian Administrative Law No. 89 Issued in 1998. Cairo, Egypt.

Egyptian Government (2018). Egyptian Administrative Law No. 182 Issued in 2018. Cairo, Egypt.

Ingle, P. V., Mahesh, G., & M.D, D. (2021). Identifying the performance areas affecting the project performance for Indian construction projects. Journal of Engineering, Design and Technology, 19(1), 1–20. doi:10.1108/JEDT-01-2020-0027.

Najjar, M. K., Figueiredo, K., Evangelista, A. C. J., Hammad, A. W. A., Tam, V. W. Y., & Haddad, A. (2022). Life cycle assessment methodology integrated with BIM as a decision-making tool at early-stages of building design. International Journal of Construction Management, 22(4), 541–555. doi:10.1080/15623599.2019.1637098.

Khalef, R., & El-adaway, I. H. (2021). Automated Identification of Substantial Changes in Construction Projects of Airport Improvement Program: Machine Learning and Natural Language Processing Comparative Analysis. Journal of Management in Engineering, 37(6). doi:10.1061/(asce)me.1943-5479.0000959.

Ahmed, M. E. K., & Girgs, I. R. N. (2023). A comparative study on achieving universally designed schools. Two case studies at Aswan city, Egypt. International Journal of Construction Management, 23(12), 2102–2115. doi:10.1080/15623599.2022.2042645.

Othman, A. A. E., & Khalil, M. H. M. (2020). A lean talent management framework for maximizing creativity in architectural design firms. International Journal of Construction Management, 20(5), 520–533. doi:10.1080/15623599.2018.1490865.

Barlow, R. P. G., Fisher, G. N., & Bowman, N. I. (2001). Reducing the Adversarial Nature of Consultation with Stakeholders: A Methodology to Help in the Design and Construction Stages of Construction Projects. International Journal of Construction Management, 1(1), 77–81. doi:10.1080/15623599.2001.10773025.

Wong, P. S. P., Holdsworth, S., Crameri, L., & Lindsay, A. (2019). Does carbon accounting have an impact on decision-making in building design? International Journal of Construction Management, 19(2), 149–161. doi:10.1080/15623599.2017.1401290.

Sha’ar, K. Z., Assaf, S. A., Bambang, T., Babsail, M., & Fattah, A. M. A. El. (2017). Design–construction interface problems in large building construction projects. International Journal of Construction Management, 17(3), 238–250. doi:10.1080/15623599.2016.1187248.

Li, Y., & Ji, W. (2021). Robustness of Stakeholder Response Networks for Infrastructure System Protection. Journal of Management in Engineering, 37(6), 04021063. doi:10.1061/(asce)me.1943-5479.0000960.

Beardmore, D. C., & Molenaar, K. R. (2023). Roadway design and construction in infrastructure limited contexts: a risk breakdown structure. International Journal of Construction Management, 23(10), 1675–1683. doi:10.1080/15623599.2021.1999768.

Saghatforoush, E., Hosseini Nourzad, S. H., Zareravasan, A., & Jadidoleslami, S. (2023). Enablers for BIM application in architectural design: a robust exploratory factor analysis approach. International Journal of Construction Management, 23(9), 1549–1559. doi:10.1080/15623599.2021.1985775.

Forghani, R., Sher, W., & Kanjanabootra, S. (2023). Critical technical design principles for maximizing the reuse of building components. International Journal of Construction Management, 23(7), 1187–1195. doi:10.1080/15623599.2021.1959126.

Manoj, G., & Shivaji, C. Y. (2010). Design interface management of airport projects. International Journal of Construction Management, 10(3), 29–44. doi:10.1080/15623599.2010.10773148.

Mitropoulos, P., & Tajima, V. (2022). Constructability opportunities in the engineering design of marine pier structures: a case study. International Journal of Construction Management, 22(3), 366–378. doi:10.1080/15623599.2019.1624677.

García de Soto, D. B., Streule, T., Klippel, M., Bartlomé, O., & Adey, B. T. (2020). Improving the planning and design phases of construction projects by using a Case-Based Digital Building System. International Journal of Construction Management, 20(8), 900–911. doi:10.1080/15623599.2018.1502929.

Xia, B., Chan, A. P. C., & Skitmore, M. (2012). A classification framework for design-build variants from an operational perspective. International Journal of Construction Management, 12(3), 85–99. doi:10.1080/15623599.2012.10773196.

Taher, A. H., & Elbeltagi, E. E. (2023). Integrating building information modeling with value engineering to facilitate the selection of building design alternatives considering sustainability. International Journal of Construction Management, 23(11), 1886–1901. doi:10.1080/15623599.2021.2021465.

Zhang, N., Wang, J., Al-Hussein, M., & Yin, X. (2023). BIM-based automated design of drainage systems for panelized residential buildings. International Journal of Construction Management, 23(15), 2683–2698. doi:10.1080/15623599.2022.2085853.

Paik, S. mok, Leviakangas, P., & Choi, J. (2022). Making most of BIM in design: analysis of the importance of design coordination. International Journal of Construction Management, 22(12), 2225–2233. doi:10.1080/15623599.2020.1774837.

Manu, P., Poghosyan, A., Agyei, G., Mahamadu, A. M., & Dziekonski, K. (2021). Design for safety in construction in sub-Saharan Africa: a study of architects in Ghana. International Journal of Construction Management, 21(4), 382–394. doi:10.1080/15623599.2018.1541704.

Rohman, M. A., & Wiguna, I. P. A. (2021). Evaluation of road design performance in delivering community project social benefits in Indonesian PPP. International Journal of Construction Management, 21(11), 1130–1142. doi:10.1080/15623599.2019.1603095.

Ramani, P. V., & Lingan, L. K. (2022). Developing a lean model to reduce the design process cost of gas insulated switchgear foundation using value stream mapping–a case study. International Journal of Construction Management, 22(4), 669–677. doi:10.1080/15623599.2019.1644756.

Singh Rajput, T., & Thomas, A. (2023). Optimizing passive design strategies for energy efficient buildings using hybrid artificial neural network (ANN) and multi-objective evolutionary algorithm through a case study approach. International Journal of Construction Management, 23(13), 2320–2332. doi:10.1080/15623599.2022.2056409.

Lam, E. W. M., Chan, A. P. C., & Chan, D. W. M. (2007). An Empirical Study on the Problems of Running Design and Build Projects in Construction. International Journal of Construction Management, 7(1), 1–15. doi:10.1080/15623599.2007.10773091.

Shrestha, P. P., & Mani, N. (2014). Impact of Design Cost on Project Performance of Design-Bid-Build Road Projects. Journal of Management in Engineering, 30(3). doi:10.1061/(asce)me.1943-5479.0000220.

Wasim, M., Vaz Serra, P., & Ngo, T. D. (2022). Design for manufacturing and assembly for sustainable, quick and cost-effective prefabricated construction–a review. International Journal of Construction Management, 22(15), 3014–3022. doi:10.1080/15623599.2020.1837720.

Zhikun, D., Fungfai, N. G., & Jiayuan, W. (2010). Personal construct based factors affecting willingness to share knowledge between architects in a project design team. International Journal of Construction Management, 10(3), 1–11. doi:10.1080/15623599.2010.10773146.

Yuce, B., Mastrocinque, E., Packianather, M. S., Pham, D., Lambiase, A., & Fruggiero, F. (2014). Neural network design and feature selection using principal component analysis and Taguchi method for identifying wood veneer defects. Production and Manufacturing Research, 2(1), 291–308. doi:10.1080/21693277.2014.892442.

Kritikos, M., Concepción Maure, L., Leyva Céspedes, A. A., Delgado Sobrino, D. R., & Hrušecký, R. (2019). A Random Factorial Design of Experiments Study on the Influence of Key Factors and Their Interactions on the Measurement Uncertainty: A Case Study Using the ZEISS CenterMax. Applied Sciences, 10(1), 37. doi:10.3390/app10010037.

Kiritani, M. (1999). Design of experiments on production and reaction of point defects. Radiation Effects and Defects in Solids, 148(1), 233–267. doi:10.1080/10420159908229096.

Gade, A. N., Jensen, R. L., Larsen, T. S., Nissen, S. B., & Andresen, I. (2021). Value-based decision making in the pre-design stage of sustainable building renovation projects–exploring two methods for weighting criteria. International Journal of Construction Management, 21(6), 648–663. doi:10.1080/15623599.2019.1578913.

Lewis, C. D. (1982). Industrial and business forecasting methods: A practical guide to exponential smoothing and curve fitting. Butterworth Scientific, Teddington, United Kingdom.


Full Text: PDF

DOI: 10.28991/CEJ-SP2023-09-017

Refbacks

  • There are currently no refbacks.




Copyright (c) 2022 Ahmed Nouh, El-Sayed El-Kasaby, Khaled Aboulata

Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License.
x
Message